Customer: | Sakmtavarenergo |
Gen. Designer: | Sakhydroenergomsheni |
Gen. Contractor: | Sakhydroenergomsheni |
Subcontractor: | Tbilsresmsheni |
Techn. Assistance / service Of Gen. Contractor: |
Orgenergomsheni |
№ | Buildings | Designation of works | S e r v i c e s | Period of works, years | ||||
---|---|---|---|---|---|---|---|---|
Unity | Quantity | Inspection of preparation, transportation and first test works | Inspection of welding and mounting works | Consulting service of welding works | ||||
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 |
1 | Spillway Dam of Rioni HPP | Preparation of 4 new Gates in Tbilisi and Rustavi Factories (consisted of 2 parts each) - weight - size |
t m |
4X76=304 10,2x11,25 |
+ | - | - | 2000 |
2 | Transportation from Tbilisi and Rustavi Factories 4 Gates to the site Spillway Dam | t·km | 4x304x270 | + | - | + | ||
3 | Dismantling of the 4 amortised Gates from all 4 spans of Sillway Dam - weight |
t | 4X79,5=318 | - | + | + | ||
4 | Repair guide tracks for Gates in all 4 spaces | 4 compl. | acc. instr. | - | + | + | ||
5 | Mounting of the new Gates in all 4 spaces (2 parts each) | 4 compl. | 4x76=304 | - | + | + | ||
6 | Treatment of the contact surfaces each part Gates before welding of joints | 4 compl. | acc. instr. | - | + | + | ||
7 | Welding of joints and its painting | 4 compl. | acc. design | - | + | + | ||
8 | Installation of wheels and rubber packing | 4 compl. | acc. instr. | - | + | + | ||
9 | All tests | - | - | - |